Blockbuster. Construction in progress.

“SILPO” area

The basic works for perimeter closing have been done.

Actively in progress:

  • installation of smoke removal systems,
  • preparatory work for the installation of automatic sprinkler systems.



The works of the layout of all the technical premises have been done.

The works of internal installation of metal structure’s stairs have been done.

The installation of the restaurant’s metal structures in a recreation area is at the stage of completion (800m2).

The installation of automatic sprinkler systems, ventilation systems and smoke removal system is nearing completion.

Works for the decorative painting of the roof’s metal structures have been made by 80%.

The full set of “Roller Coaster” constructions has been delivered at the object.

The preparatory work for the installation is carried out at the moment.